Grade P1 plate
Unit: tons
Short
Usable on hand
20 tons
Usable on 2026-12-01
Inbound to come
15 tons
PO-202 arrives 2026-12-12
Balance ledger
Arrivals count before demand on the same date. A receipt counts only from its arrival date.
| Date | Line | Change | Current plan | With proposal | Mark |
|---|---|---|---|---|---|
| Date | Usable on hand | Change20 tons | Current plan20 tons | With proposal20 tons | Mark– |
| Date | Demand SO-101 | Change−30 tons | Current plan-10 tons | With proposal-10 tons | MarkShort |
| Date | Arrival PO-202 | Change+15 tons | Current plan5 tons | With proposal5 tons | Mark– |
Latest order date = first short date 2026-12-10 minus 56 days lead time.
Replenishment compare
Shortage, current plan: 10 tons → with proposal: 10 tons
Proposals stay apart from the plan until you accept one. Nothing is purchased.
No proposals. Add one to compare coverage.