Coverage board

Firm orders and confirmed arrivals only. Arrivals count before demand on the same date.

Exception queue

4 grades go short · sorted by first short date

Grades that go short on current firm orders, earliest first
Grade P1 plateReviewedFirst shortDeficit10 tonsLatest order dateNew purchase in timeNoSource linesSO-101PO-202Open
Grade S3 sheetOpenFirst shortDeficit7 tonsLatest order dateNew purchase in timeYesSource linesSO-104PO-201Open
Grade A1 alloyReviewedFirst shortDeficit7 tonsLatest order dateNew purchase in timeNoSource linesSO-103Open
Grade P4 plateOpenFirst shortDeficit13 tonsLatest order dateNew purchase in timeNoSource linesSO-110SO-105SO-106PO-204Open

Latest order date = first short date minus lead time. New purchase in time = simulated today plus lead time on or before the first short date. Lead times and buffers are your own assumptions.

All grades

Inbound counts only from its arrival date. Units are never totalled across grades.

Grades with usable stock, inbound, buffer, lead time and status
Grade P1 plateUsable on hand20 tonsInbound15 tonsArrivesBuffer5 tonsLead time56 daysStatusShort
Grade A1 alloyUsable on hand5 tonsInboundNoneArrives–Buffer2 tonsLead time56 daysStatusShort
Grade P4 plateUsable on hand30 tonsInbound10 tonsArrivesBuffer6 tonsLead time56 daysStatusShort
Grade S3 sheetUsable on hand5 tonsInbound10 tonsArrivesBuffer4 tonsLead time3 daysStatusShort
Grade S2 barUsable on hand0 tonsInbound10 tonsArrivesBuffer0 tonsLead time3 daysStatusCovered
Grade F6 flat barUsable on hand120 mInbound100 mArrivesBuffer20 mLead time3 daysStatusBelow buffer

All plants, orders and suppliers are fictional. Nothing here is purchased.

Planners' scenarios

Every visitor works in their own scenario. Open one to look at it.