Grade S3 sheet
Unit: tons
Short
Usable on hand
5 tons
Usable on 2026-12-01
Inbound to come
10 tons
PO-201 arrives 2026-12-20
Balance ledger
Arrivals count before demand on the same date. A receipt counts only from its arrival date.
| Date | Line | Change | Current plan | With proposal | Mark |
|---|---|---|---|---|---|
| Date | Usable on hand | Change5 tons | Current plan5 tons | With proposal5 tons | Mark– |
| Date | Proposed | Change+10 tons | Current plannot in plan | With proposal15 tons | Mark– |
| Date | Demand SO-104 | Change−12 tons | Current plan-7 tons | With proposal3 tons | MarkShort |
| Date | Arrival PO-201 | Change+10 tons | Current plan3 tons | With proposal13 tons | Mark– |
Latest order date = first short date 2026-12-15 minus 3 days lead time.
Replenishment compare
Shortage, current plan: 7 tons → with proposal: 0 tons
Proposals stay apart from the plan until you accept one. Nothing is purchased.
- Proposed10 tons arriving
Accept adds to the fictional plan. Nothing is purchased.