Material coverage

Simulated today

Export CSV

Coverage board

Grade P1 plate

Unit: tons

Short

Viewing the scenario of nickstreicher+e2e-prospect-demos@gmail.com (read only).

Usable on hand

20 tons

Usable on 2026-12-01

Inbound to come

15 tons

PO-202 arrives 2026-12-12

tons

Your assumption. Enter to save.

days

Supplier lead time, your assumption.

Balance ledger

Arrivals count before demand on the same date. A receipt counts only from its arrival date.

Usable stock, arrivals and firm demand for Grade P1 plate in date order, with the running balance
DateUsable on handChange20 tonsCurrent plan20 tonsWith proposal20 tonsMark–
DateDemand SO-101Change−30 tonsCurrent plan-10 tonsWith proposal-10 tonsMarkShort
DateArrival PO-202Change+15 tonsCurrent plan5 tonsWith proposal5 tonsMark–

Latest order date = first short date 2026-12-10 minus 56 days lead time.

Replenishment compare

Shortage, current plan: 10 tons → with proposal: 10 tons

Proposals stay apart from the plan until you accept one. Nothing is purchased.

No proposals. Add one to compare coverage.