Material coverage

Simulated today

Export CSV

Coverage board

Grade P4 plate

Unit: tons

Short

Viewing the scenario of nickstreicher+e2e-prospect-demos@gmail.com (read only).

Usable on hand

30 tons

Usable on 2026-12-01

Inbound to come

10 tons

PO-204 arrives 2027-01-20

tons

Your assumption. Enter to save.

days

Supplier lead time, your assumption.

Balance ledger

Arrivals count before demand on the same date. A receipt counts only from its arrival date.

Usable stock, arrivals and firm demand for Grade P4 plate in date order, with the running balance
DateUsable on handChange30 tonsCurrent plan30 tonsWith proposal30 tonsMark–
DateDemand SO-110Change−5 tonsCurrent plan25 tonsWith proposal25 tonsMark–
DateDemand SO-105Change−18 tonsCurrent plan7 tonsWith proposal7 tonsMark–
DateDemand SO-106Change−20 tonsCurrent plan-13 tonsWith proposal-13 tonsMarkShort
DateArrival PO-204Change+10 tonsCurrent plan-3 tonsWith proposal-3 tonsMark–

Latest order date = first short date 2027-01-12 minus 56 days lead time.

Replenishment compare

Shortage, current plan: 13 tons → with proposal: 13 tons

Proposals stay apart from the plan until you accept one. Nothing is purchased.

No proposals. Add one to compare coverage.